13.91Removing dry or oil bound distemper, water proofing cement paint and the like by scrapping, sand papering and preparing the surface smooth including necessary repairs to scratches etc. complete.
Matches DSR 2023Vol 2, pages 1048 to 1049
Rate per sqm
25.15
DSR 2023
How this rate is built5 items, 4 additional charges
LabourBhisti, Beldar, Coolie
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis