14.3Fixing chowkhat in existing opening in brick/ RCC wall with dash fasteners/Chemical fasteners of appropriate size (3 nos on each vertical member of door chowkhat and 2 nos on each vertical member of window chowkhats), including Cost of dash fasteners/ chemical fastener.
Matches DSR 2023Vol 2, page 1074
Rate per each
217.10
DSR 2023
How this rate is built7 items, 4 additional charges
MaterialDash fastener / Chemical fastener
LabourBeldar, Coolie, Mate, Mistry
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
For door/ window/ clerestory window · Making the opening in brick masonry including dismantling in floor or walls by cutting masonry and making good the damages to walls, flooring and jambs complete, to match existing surface i/c disposal of mulba/ rubbish to the nearest municipal dumping ground, all complete as per direction of Engineer-in-Charge.