16.85Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost)
Matches DSR 2023Vol 2, page 1315
Rate per metre
109.45
DSR 2023
How this rate is built5 items, 4 additional charges
MaterialPortland Cement (OPC-43 Grade), Coarse sand (zone III), Carriage of Coarse sand, Carriage of Cement
LabourBhisti, Beldar, Coolie, Mason 1st class, Mason 2nd class
Built from1 other item in this book
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.