26.37Cleaning of exposed concrete surface of sticking material including loose and foreign material by sand blasting with coarse sand followed by and including cleaning with oil free air blast as per direction of Engineer in charge.
Matches DSR 2023Vol 2, pages 2021 to 2022
Rate per sqm
382.40
DSR 2023
How this rate is built6 items, 4 additional charges
MaterialCoarse sand (zone III), Carriage of Coarse sand
LabourBeldar
MachineryHire charges of sand blasting equipment, Hire charges of compressor
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.