Centering and shuttering including strutting, propping etc. and removal of form work for :
4.3.3Columns, piers, abutments, pillars, posts and struts
Matches DSR 2023Vol 1, pages 177 to 178
Rate per sqm
961.30
DSR 2023
How this rate is built10 items, 4 additional charges
MaterialWall form panel 1250x450 mm, Corner angle 45x45x5 mm 2.50 m long, Column clamp 450x1070 mm, Prop 2 m ( 2-3.5 m)
LabourBeldar, Fitter (grade 1)
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.