Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete upto plinth level.
5.22B.1Thermo-Mechanically Treated bars of grade Fe-500D or more.
Matches DSR 2023Vol 1, pages 279 to 280
Rate per kg
99.65
DSR 2023
How this rate is built7 items, 4 additional charges
MaterialTwisted steel/ deformed TMT bars Fe-500D, Carriage of Steel
LabourBlacksmith 1st class, Beldar
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
Extra for rendering smooth the top of suspended floors, landings and staircases (treads and risers) with cement mortar 1:2 (1 cement : 2 coarse sand), including a floating coat of neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15 mm of fine sand in case of suspended floor and bricks laid in mud mortar in case of landings and steps, including subsequent removal and cleaning of the same.