Centering and shuttering including strutting, propping etc. and removal of form for
5.9.1Foundations, footings, bases of columns, etc. for mass concrete
Matches DSR 2023Vol 1, page 230
Rate per sqm
392.15
DSR 2023
How this rate is built12 items, 4 additional charges
MaterialWall form panel 1250x500 mm, Corner angle 45x45x5 mm 1.50 m long, 100 mm channel shoulder 2.5 m long, Double clip (bridge clip), Single clip, M.S. tube 40 mm dia
LabourBeldar, Fitter (grade 1)
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.