6.41Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof.
Matches DSR 2023Vol 1, page 357
Rate per sqm
181.15
DSR 2023
How this rate is built1 item, 4 additional charges
LabourCoolie
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
Cement mortar 1 : 4 (1 cement : 4 coarse sand) · Half brick masonry with non modular fly ash bricks of class designation 10, conformingio IS :12894, in super structure above plinth upto floor V level.