7.34Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored).
Matches DSR 2023Vol 1, pages 399 to 400
Rate per depth
1,098.80
DSR 2023
How this rate is built2 items, 4 additional charges
LabourBeldar
MachineryHire charges of Pump set of capacity 4000 litres/hour
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.