Open the menu
Hide the sidebar
Rate
Analyser
Opening…
Back
Search
/
Sub head 14
/
14.16.1.2
Not exceeding 4.00 metres in length.
14.16.1.2
Hollock wood beams
Matches DSR 2023
Vol 2, pages 1085 to 1086
Rate per cum
70,271.70
DSR 2023
How this rate is built
21 items, 4 additional charges
Material
Safeda ballies 125 mm diameter, Oil type wood preservative, Carriage of Timber, Hollock wood in scantling 10
Labour
Bandhani, Carpenter 2nd class, Beldar, Coolie, Painter, Mason (average)
Loading
Water 1%
GST
CPOH 15%
Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
Sign in and unlock 3 items free
See prices
Near this item in the book
14.14.1
Red/ white sand stone slabs 30 to 50 mm thick
· Replacing sand stone slabs in roofing, laid in cement mortar 1:4 (1 cement : 4 coarse sand), including necessary repairs and cement pointing with same mortar complete, including disposal of rubbish to dumping ground, all complete as per direction of Engineer-in-Charge.
14.15.1
Sal wood battens
· Renewing wooden battens in roofs, including making good the holes in wall and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge.
14.16.1.1
Sal wood beams
· Not exceeding 4.00 metres in length.
14.16.1.2
This item
14.16.2.1
Sal wood beams
· Above 4.00 metres and upto 5.00 metres length.
14.16.2.2
Hollock wood beams
· Above 4.00 metres and upto 5.00 metres length.
14.17
Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge.