14.17Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge.
Matches DSR 2023Vol 2, page 1088
Rate per sqm
72.45
DSR 2023
How this rate is built4 items, 4 additional charges
LabourBhisti, Beldar, Coolie
Loading
Water 1%GSTCPOH 15%Cess 1%