15.25Dismantling stone slab flooring laid in cement mortar including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.
Matches DSR 2023Vol 2, pages 1149 to 1150
Rate per sqm
266.45
DSR 2023
How this rate is built3 items, 4 additional charges
LabourBeldar, Coolie
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis