15.32Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 metres lead.
Matches DSR 2023Vol 2, page 1153
Rate per sqm
57.70
DSR 2023
How this rate is built2 items, 4 additional charges
LabourBeldar
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.