15.33Dismantling wooden ballies in posts and struts including stacking within 50metres lead.
Matches DSR 2023Vol 2, page 1153
Rate per metre
20.95
DSR 2023
How this rate is built3 items, 4 additional charges
LabourBeldar, Coolie
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.