15.58Demolishing R.C.C. work by mechanical means and stockpiling at designated locations and disposal of dismantled materials up to a lead of 1 kilometre, stacking serviceable and unserviceable material separately including cutting reinforcement bars.
Matches DSR 2023Vol 2, pages 1174 to 1175
Rate per cum
2,818.90
DSR 2023
How this rate is built8 items, 4 additional charges
MachineryTractor with trolley, Air compressor 250 cfm with two leads for pneumatic cutters /, Joint cutting machine with 2-3 blades
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earthwith lead upto 50 metres.