15.59Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre, as per direction of Engineer-in-charge.
Matches DSR 2023Vol 2, page 1175
Rate per cum
420.80
DSR 2023
How this rate is built4 items, 4 additional charges
LabourBeldar, Mate
MachineryTractor with ripper attachment, Tractor with trolley
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.