16.2Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density).
Matches DSR 2023Vol 2, pages 1179 to 1180
Rate per cum
24.85
DSR 2023
How this rate is built4 items, 4 additional charges
LabourBhisti, Chowkidar
MachineryHire charges of Diesel Road Roller - 8 to 10 tonne
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.