2.27Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete.
Matches DSR 2023Vol 1, page 132
Rate per cum
2,123.75
DSR 2023
How this rate is built5 items, 4 additional charges
MaterialCarriage of sand, Sand zone V (Jamuna)
LabourBhisti, Beldar, Coolie
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
· Excavating holes more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m.