2.25(a)Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift.
Vol 1, pages 130 to 131
Rate per cum
700.50
DSR 2023
How this rate is built7 items, 4 additional charges
MaterialRoyalty for good earth
LabourBhisti, Beldar, Coolie, Mate
MachineryHydraulic Excavator (3D) with driver and fuel
Built from1 other item in this book
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.