Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor.
26.77.1Prestressed hollow core Slab up to 200 mm thickness
Matches DSR 2023Vol 2, page 2082
Rate per sqm
203.50
DSR 2023
How this rate is built9 items, 4 additional charges
MachineryHire & running charge for crane upto 40 tonne capacity, Generator 100 KVA/125 KVA
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.