6.24Extra for laying brick work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soil water level up to the centre of gravity of brick work under sub - soil water with the quantity of brick work in cum. executed under the sub - soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored).
Matches DSR 2023Vol 1, page 342
Rate per depth
1,098.80
DSR 2023
How this rate is built2 items, 4 additional charges
LabourBeldar
MachineryHire charges of Pump set of capacity 4000 litres/hour
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.
· Brick work with common burnt clay selected F.P.S. (non modular) bricks of class designation 7.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)