2.38Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge.
Matches DSR 2023Vol 1, page 142
Rate per cum
308.20
DSR 2023
How this rate is built3 items, 4 additional charges
LabourBhisti, Coolie, Mate
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.