Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position with necessary stainless steel screws etc.
9.3.2Kiln seasoned and chemically treated hollock wood
Matches DSR 2023Vol 1, pages 462 to 463
Rate per cum
71,337.85
DSR 2023
How this rate is built7 items, 4 additional charges
MaterialCarriage of Timber, Hollock wood in scantling 10, Kiln seasoning of timber
LabourCarpenter 2nd class, Beldar
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.