Extra for additional labour for circular works, such as in frames of fan light
9.4.2Sal wood
Matches DSR 2023Vol 1, pages 463 to 464
Rate per cum
11,652.05
DSR 2023
How this rate is built4 items, 4 additional charges
MaterialSal wood in scantling 10, Carriage of Timber
LabourBeldar, Carpenter (average)
Loading
Water 1%GSTCPOH 15%Cess 1%
View full rate analysis
See every quantity and rate, and the 4 additional charges with the amount each one is worked out on. Change any rate to see the updated cost, then download the complete working as an Excel file.